AGL's plan to replace Liddell is cheaper and cleaner than keeping it open

  • Written by Kriti Nagrath, Senior Research Consultant, University of Technology Sydney

The Commonwealth government called last week for AGL Energy to consider selling its Liddell power station to rival Alinta.

Federal Energy Minister Josh Frydenberg has raised concerns that the scheduled 2022 shutdown of Liddell will affect New South Wales’ energy reliability. It’s suggested the sale would provide a way to keep the ageing power station open past the end of its normal 50-year operating life.

However, AGL responded to government concerns in December 2017 by releasing a replacement plan. Liddell’s theoretical maximum output is 1,800 megawatts (MW), but the firm capacity – the power that can be relied upon at peak time – is 1,000 MW. AGL is confident this can be replaced by a mix of improved efficiency, renewables and demand response.

AGL’s proposal unpacked

Late last year, in response to the Commonwealth government’s pressure, AGL updated its Liddell replacement plan. The updated plan includes generator efficiency upgrades, new natural gas and renewable energy generation capacity, and demand response.

This plan builds on the planned 2022 closure of the Liddell station. Phased investments in new, low-emissions generation and upgrades to existing generation will replace the 1,000 MW of coal-fired power by:

  • increasing the capacity of AGL’s nearby Bayswater coal-fired power station by 100MW
  • installing 750MW of high-efficiency gas power (at potential sites in Newcastle and/or elsewhere in NSW)
  • adding 1,600MW of new renewable generation capacity (wind and solar farms)
  • providing 100MW of firm capacity from demand response and 250MW from battery storage.

The replacement portfolio is split into three stages. The first aims for 550MW of new generation: 300MW from two solar power plants, to be built by third-party developers, and 250MW from a new gas peaking power station located at Newcastle (or other suitable sites in NSW).

Further, AGL has already approved 650MW of wind projects. The Bayswater efficiency upgrade will add 100MW to the capacity without burning any additional coal.

This, along with the 20MW of demand response, will provide the “firm capacity” required to meet existing customer needs, in line with the federal National Energy Guarantee. The “firm capacity factor” is the proportion of the installed capacity (the theoretical maximum) that can be relied upon to be available at peak time.

The next two stages will progressively add new capacity from renewables, battery storage and demand response to meet the energy needs of AGL’s potential uncontracted customers. Stage 2 and Stage 3 feasibility is expected to start by 2020 and 2021 respectively, for a 2022 delivery.

AGL is relying on the market

AGL’s Liddell replacement plan is designed to provide an equivalent amount of energy and dispatchable power at a similar level of reliability.

The plan’s total investment of A$1.36 billion is more than the A$920 million estimate of the 2027 Liddell extension plan, but once operating and fuel costs are included the average cost of replacement generation is more affordable at A$83 per megawatt hour (MWh), compared with extending the life of Liddell at A$106 per MWh.

AGL's plan to replace Liddell is cheaper and cleaner than keeping it open Levelised cost of energy based on information sourced by AGL including: the capital cost of the Liddell life extension works as advised by Worley Parsons (Advisian). AGL’s discount rate in line with their commercial target returns. Westpac Banking Corporation’s forecast of the Newcastle coal price discounted based on the lower calorific value required for power station coal. A carbon emissions cost has been included as per AEMO’s ‘moderate’ 2015 scenario. AGL's NSW Generation Plan

Though the replacement plan has an installed capacity of 2,900MW, it accounts for a firm capacity of 1,000MW.

The Australian Energy Market Operator has endorsed AGL’s Liddell replacement plan. It said the plan provides more than enough energy and capacity to meet the potential shortfall created by the closure if AGL completes all three stages by the 2022 deadline.

Some of this plan is already under way, as the AGL board has approved the upgrades at Bayswater and Liddell and the new solar and wind power plants. However, the next two stages are dependent on market signals and investments other companies make in new resources.

If stages 2 and 3 of AGL’s plan are not undertaken in time and other market players do not invest, there could be a reliability gap that results in supply interruptions. While this is unlikely to occur, this is exactly the type of problem that the government’s National Energy Guarantee is supposed to fix. The guarantee envisions that retailers carry the responsibility of meeting the required amount for dispatchable energy. Failure to do so would invite financial penalties, with the energy market operator stepping in as the procurer of last resort.

However, AGL has proposed an adequate plan to meet the gap that the Liddell closure would create. It’s ultimately improbable that regulator intervention will be needed.

That said, AGL’s plan is not necessarily the best plan. There are other lower-emission options that are more cost-effective.

A study by the Institute for Sustainable Futures (which I have contributed to) proposes a third “clean energy package”, including renewable energy, energy efficiency, energy storage, demand response and flexible pricing. Rather than selling Liddell, if the Commonwealth is looking for low-cost and reliable solutions, this is the approach it should be pursuing.

Authors: Kriti Nagrath, Senior Research Consultant, University of Technology Sydney

Read more http://theconversation.com/agls-plan-to-replace-liddell-is-cheaper-and-cleaner-than-keeping-it-open-94651

Bottle Label Printing: Key Factors to Consider Before Your Next Packaging Run

Effective packaging begins with understanding the product, bottle material, artwork and production requirements when planning bottle label printing. H...

Planning a Long-Distance Move With Interstate Movers Melbourne

Moving between states involves more planning than a typical local relocation. Along with packing and transporting household belongings, you need to...

Understanding the Role of an I/O Controller in Industrial Automation

Modern industrial systems depend on accurate communication between sensors, machines and control systems. An I/O controller can help manage this commu...

How the Right Mining Hose Supports Demanding Operations

Mining environments place considerable demands on equipment used for material transfer, water management and processing. Hoses operating in these co...

Simple Ideas for Making Social Gatherings More Memorable

We have all been to those parties where everyone just stands around the kitchen island, staring at their phones, waiting for someone else to make a mo...

Outdoor Wall Lights: Improving Exterior Lighting Around Your Home

Lighting can influence how a room looks, feels and functions, so the right fitting should be selected according to both appearance and practical req...

Commercial Office Cleaning: Combining Routine Office Cleaning With Melbourne Service

Keeping a workplace clean requires a service that can accommodate everyday tasks as well as the particular needs of the business. Professional comme...

Caravan Sales in Queensland: How to Find the Right Caravan for Sale QLD

Caravan ownership is about more than having somewhere to sleep while travelling. For many Queenslanders, it is one of the best ways to explore regio...

What Sir Walter Buffalo Turf Actually Costs in 2026 (And Why Quotes Vary So Much)

Two quotes landed on a Hills District homeowner's kitchen table last spring for the exact same 80-square-metre backyard. One said $12 a metre. The o...

Nearly 1,300 NSW Hospital Beds Are Occupied By People Who Are Ready To Go Home

1,276 people in NSW hospitals have been medically cleared for discharge but remain in hospital because they're still waiting for NDIS or aged care sup...

National Survey Launched to Measure Operational Impacts of Federal NDIS Policy Reforms

The effects of recent NDIS reforms are beginning to move beyond policy papers and into day to day service delivery. A new national survey is asking ...

Beyond the Nappy Cake: Baby Shower Gifts That Get Used

What new Australian parents unwrap, keep, and quietly thank you for months later. Six weeks after my daughter was born, I did an audit of the baby sh...

Parent-Advocates Are Reshaping Frontline Disability Service Delivery

Parents have always been part of the disability sector. They advocate, coordinate services, challenge decisions and often become the person holding ev...

Vista Cruises Enters "Two-Flagship Era" as Vista Aurora Completes Inaugural Voyage

Vista Aurora Sets Sail along the Yangtze. (Photo courtesy of the company)YICHANG, China — August 5, 2026 — Vista Aurora, a high-end interprovinc...

A Digital Preparation Checklist For International Medical Conferences

An international medical conference compresses many responsibilities into a few days. A delegate may need to present research, move between venues, ...

The Growing Popularity of Lab Grown Diamonds in Sydney and Hong Kong

The diamond industry has changed significantly in recent years as more buyers seek ethical, affordable, and sustainable alternatives to mined diamon...

Modern AI SEO Agency vs Traditional SEO: What’s the Difference

Search engine optimisation has changed dramatically over the past few years. Search engines have become smarter, user behaviour has evolved, and bus...

Caravan Travel for Modern Australian Getaways: Plan a Comfortable Holiday

A family road trip is one of the best ways to explore Australia together. And, travelling by caravan gives you the freedom to take your time, stop a...