West Gate Tunnel saga shows risk of 'lock-in' on mega-projects pitched by business

  • Written by James Whitten, Ph.D Candidate, Faculty of Architecture, Building and Planning, University of Melbourne

Victoria’s government finds itself in a big hole with its West Gate Tunnel project. As diggers lie idle in a dispute over what to do with contaminated soil, it’s facing long delays and billions in extra costs. But the government appears locked into a contentious project that was put to it as a market-led proposal, an arrangement that bedevils transport projects across Australia.

Australian governments look increasingly to mega-projects to solve urban and regional transport problems. These projects are city-shaping. They can transform how entire urban regions function.

The public has a clear stake in these projects, but unsolicited market-led proposals are subverting planning processes that are meant to protect the public interest.

Read more: Market-led infrastructure may sound good but not if it short-changes the public

Market-led proposals are unsolicited bids to government by private firms to provide public services or infrastructure. Policies governing market-led proposals were introduced in 2014 and 2015 by state governments across Australia to promote innovation in service delivery and value for money for taxpayers.

The increasing use of market-led proposals for transport mega-projects raises important questions. How are policies governing these managed, to what end, and for whose benefit?

In Melbourne, the tensions between toll road operator Transurban and the Victorian government over the West Gate Tunnel highlight a fundamental shortcoming of market-led proposals. Bluntly, these are not suited to the planning of transport mega-projects because governments can become “locked in” with questionable benefits. Lock-in has been defined as “the escalating commitment of decision-makers to an ineffective course of action”.

The case of the West Gate Tunnel

Transurban’s builders of the West Gate Tunnel, John Holland and CPB Contractors, laid off 137 workers last month in a dispute about liability for contaminated soil. This is bad press for the state government, which touted job creation and training as key project benefits.

The dispute could add to delays and costs on top of two earlier changes related to the project. The first was a ten-year extension to Transurban’s CityLink tolling concession that will cost road users billions of dollars. The second was an increase in construction costs from A$5.5 billion to A$6.7 billion to extend tunnels to save a public park.

Explanations for the dispute include the Environmental Protection Authority tightening soil disposal requirements, difficulties determining site conditions during the environmental assessment process, and insufficient foresight and planning for these risks.

Another explanation for what happened is “lock-in”. Evidence of lock-in on the West Gate Tunnel points to deeper systemic problems with market-led proposals for transport mega-projects in general.

How does lock-in happen?

Lock-in can occur when powerful corporations partner with governments in circumstances that enable them to exploit vulnerabilities in our public institutions. Some of these vulnerabilities include increasing reliance by governments on private finance, and the short period between elections compared to the time it takes to deliver bold public works programs.

Lock-in happens when the real decision to build a project is made well in advance of processes that are publicly declared to inform that decision. Once governments are locked in to a project, it can make alternatives appear increasingly unviable, if not unthinkable.

There is strong evidence to suggest this happened with the West Gate Tunnel. Significant concerns were raised early on that the project might not provide its claimed public benefits.

Read more: Impending traffic chaos? Beware the problematic West Gate Tunnel forecasts

What makes market-led proposals different?

Market-led proposals differ from government-led projects because planning is effectively outsourced to the private sector.

Market-led proposals also differ from public-private partnerships, like Melbourne’s CityLink tollway. In such cases, government plans these projects, but private firms deliver and operate them. (At least CityLink was part of a long-standing, if largely discredited, strategic plan.)

Revelations that Transurban acted in secretive and strategic ways to secure support for its West Gate Tunnel raise serious ethical questions. What does it mean to be a “good partner” to government? How should powerful private corporations obtain a “social licence” to operate?

These questions draw attention to problems inherent in Victoria’s opaque market-led proposal process. The government’s caution about the AirRail consortium’s unsolicited bid for Melbourne’s airport rail link points toward some of these dangers.

Read more: Transurban's West Gate tollway is a road into uncharted territory

What’s wrong with this approach?

Government policies for assessing market-led proposals give powerful private firms like Transurban influence over strategic planning. This contrasts with the relatively limited influence granted to affected communities and stakeholder groups advocating for sustainable transport solutions.

Acceptance of Transurban’s bid allowed a multi-billion-dollar toll road to override plans that had been taken to an election. These plans were simpler and far less expensive. The plans had been developed with the local community to better manage freight traffic by upgrading access to existing freeways.

The West Gate Tunnel process involved expedited planning that bypassed broad-based community consultation. John Holland and CPB Contractors were selected in April 2017 “to get to work” on the project. That was five months before public hearings concluded in September. Over 500 submissions were received.

Add to this the suppression of independent and critical oversight and a heavily redacted business case, and a very concerning picture of Victoria’s market-led process emerges.

Read more: Sidelining citizens when deciding on transport projects is asking for trouble

Wanted: an integrated transport plan

Because governments are ultimately responsible for their partnerships, the Victorian government should demonstrate stronger accountability and leadership. Victorians are still waiting for an integrated transport plan, as is required to be prepared under the 2010 Transport Integration Act. Instead of outsourcing transport problems to private firms, the government should develop a statewide, genuinely consultative, evidence-based plan.

An integrated transport plan would allow Victorians to see how future mega-projects, regardless of who proposes them, might serve everyone’s interests.

Authors: James Whitten, Ph.D Candidate, Faculty of Architecture, Building and Planning, University of Melbourne

Read more https://theconversation.com/west-gate-tunnel-saga-shows-risk-of-lock-in-on-mega-projects-pitched-by-business-131210

Hurstville Tutoring: Helping Students Reach Their Full Academic Potential

In a world where education is becoming increasingly competitive, students often need extra guidance to excel. For families seeking quality academic ...

A First-Time Author’s Guide to Eco-Friendly Book Printing in Melbourne

Congratulations! You’ve done the hard part: you’ve actually finished a manuscript. That alone puts you ahead of countless people who say they’ll...

The Paint Job That Sells Homes: Design That Speaks Value Before You Step Inside

A proper paint job can do much more than simply modernize the color of the walls; it can affect how implicit buyers view a home. In real estate, curb ...

Global Humanitarian Alison Thompson Named 2026 NSW Australian of the Year — Why First Aid Knowledge Matters

Global humanitarian Alison Thompson OAM has been named the 2026 Australian of the Year for New South Wales, recognised for her decades of frontline re...

Modern Roller Shutters and Electric Roller Shutters: Security, Style, and Smart Living

When it comes to home and business security, few solutions offer the same balance of protection, convenience, and style as modern roller shutters. D...

What Is a Plunge Pool? A Complete Guide for Australian Backyards

Plunge pools have become one of Australia’s most sought-after outdoor features, offering a stylish, compact, and refreshing escape for homes of all ...

Gas Ducted Heating: Efficient, Reliable, and Cost-Effective Warmth for Melbourne Homes

Melbourne’s winters are known for their biting cold, and maintaining a comfortable indoor temperature becomes a top priority for homeowners. While...

Common Commercial Leasing Mistakes and How to Avoid Them

Leasing a commercial property is a major commitment that can shape the future of a business. Yet, many tenants and landlords overlook key details th...

Laser Skin Tightening: The Non-Surgical Way to Restore Youthful, Firm Skin

As we age, our skin naturally begins to lose its elasticity and firmness due to reduced collagen and elastin production. For those seeking to restor...

Car Rental Mistakes Most People Make

Car rental appears to be easy, but most travellers unintentionally get stuck in usual pitfalls that incur unnecessary expense and tension. Unseen ch...

Choosing the Right Aircon Store in Brisbane Northside

Picking the right air conditioning unit for your home is only half the battle. Just as crucial is finding a top-notch air conditioning store to back i...

Split System Maintenance Tips for Better Efficiency

Split system air conditioners are a staple in homes across Brisbane Northside, and for good reason. They are a cost effective, energy efficient soluti...

Nutifood, GippsNature Launch First Product in Vietnam - Australia Partnership

Executives from both companies expressed confidence in the roadmap’s long-term impact The debut signals stronger cross-border ambitions in premiu...

How Working with Lawyers Can Strengthen Your Legal Position

Engaging experienced lawyers in Melbourne is important when dealing with legal matters. Whether it involves business, property or personal law, the ...

The Role of Cantilever Racking in Handling Long and Bulky Items

In industries that handle oversized materials, finding the right storage system is essential for safety and efficiency. This is where cantilever rac...

House Builders Melbourne: Expert Craftsmanship for Modern Living

Building a home is more than just a construction project — it’s about creating a space where families grow, memories are made, and lifestyles ev...

Seamless Business Relocations Made Easy with Office Movers in Gold Coast

Relocating an office is a complex process that requires careful planning, coordination, and execution. From moving delicate electronics to arranging f...

DIY Air Conditioning Risks & How to Avoid Costly Repairs

When the scorching Queensland heat kicks in, the urge to grab a screwdriver and tackle your air conditioner fix to yourself is totally understandable...