  • Written by: Michelle Grattan, Professorial Fellow, University of Canberra

The Albanese government’s infrastructure review has recommended 82 projects should be cancelled, after finding the $120 billion program unsustainable in its current form.

Construction has not started on these projects. The review recommends the savings be used to provide “headroom” in the program which is facing a large cost overrun.

The review recommended 100 projects, not yet under construction, should go ahead, while a further 56, also unstarted, should proceed but on the basis that identified risks are addressed satisfactorily.

Thirty six projects, not under construction, should complete planning, detailed costings, and rescoping, with the allocated funding used for “headroom”, the review says.

The government says it accepts all the review’s recommendations in principle and will announce details on Thursday.

The review estimates a $32.8 billion cost blowout in the program, of which an estimated $14.2 billion is on projects not yet under construction.

The report says the ten-year pipeline of projects “cannot be delivered within the $120 billion allocation, even with current contributions from jurisdictions”.

“The Australian Government cannot afford within the current program settings, to meet the identified cost pressures, nor add any new projects for delivery to the pipeline in the next ten years, without significant changes taking immediate effect,” the report says.

Some projects “do not demonstrate merit, lack any national strategic rationale and do not meet the Australian Government’s national investment priorities.

"In many cases, these projects are also at high risk of further cost pressures and/or delays. A number of projects were allocated a commitment of Australian Government funding too early in their planning process and before detailed planning and credible design and costing were undertaken.”

The review says the federal government can cease or pause federal funding to projects, to create “headroom for reallocation to merit-based projects, to fund construction once planning, design and detailed costings are complete or to relieve some of the estimated cost pressures on current projects”.

The government says it will not cut the overall size of the A$120 billion program. It is committing extra funding for a number of projects.

The government has been in discussions with the states and territories over the revamping of the program, with the Queensland government – which faces an election next year – warning against cuts to its state.

Among the projects the government says it is maintaining are the Melbourne Airport Rail Link, the Milton Ulladulla Bypass, the Singleton Bypass, the Muswellbrook Bypass and the Tasman Bridge Upgrade.

Authors: Michelle Grattan, Professorial Fellow, University of Canberra

Read more https://theconversation.com/infrastructure-review-recommends-culling-82-planned-projects-217805

Moving Interstate from the Gold Coast to Brisbane (or Back)? What Removalists Wish You Knew First

Have you talked to anyone who’s done the move? They say the same thing: the drive up the M1 is the easy part. It's everything around it that catches...

Why the Spring School Holidays Are a Great Time to Visit Coffs Harbour

The spring school holidays are a good time to spend a few days on the Coffs Coast. The weather is starting to warm up, there is plenty to do outdoor...

What to Do When an Older Car Is No Longer Worth Keeping in Melbourne

Ever looked at another repair quote and wondered whether your old car is still worth the trouble? It is a common turning point for Melbourne motoris...

Your Baby's First Year: A Local Guide to Feeding, Sleep, and When to Get Extra Support

Ask ten parents in a Brisbane mothers' group how their baby is feeding or sleeping, and expect ten different answers.  Someone's baby sleeps throug...

Kitchen and Laundry Makeover Ideas That Don't Require a Full Renovation

Full kitchen renos are expensive — and most people don't actually need one.  They need the kitchen to stop looking like it's stuck in 2009, or they...

How Technology Is Reshaping the Modern Australian Commercial Kitchen

The commercial kitchen has always been shaped by technology. Refrigeration changed how ingredients could be stored, modern ventilation transformed k...

The Number on a Roller Blind Fabric That Nobody Explains

Somewhere in the fabric book, next to the colour name, there is a percentage. Three per cent. Five per cent. Ten per cent. Nobody explains it, most c...

What’s Trending in Men’s Jewellery This Father’s Day!

Finding a Father’s Day gift that feels personal, stylish and genuinely wearable is not always easy. While socks and novelty mugs have traditionally ...

Road Signs: Understanding Their Role in Clear and Effective Signage

Effective signage and display hardware can help businesses communicate information, promote products and organise customer or visitor movement. Road...

Bottle Label Printing: Key Factors to Consider Before Your Next Packaging Run

Effective packaging begins with understanding the product, bottle material, artwork and production requirements when planning bottle label printing. H...

Planning a Long-Distance Move With Interstate Movers Melbourne

Moving between states involves more planning than a typical local relocation. Along with packing and transporting household belongings, you need to...

Understanding the Role of an I/O Controller in Industrial Automation

Modern industrial systems depend on accurate communication between sensors, machines and control systems. An I/O controller can help manage this commu...

How the Right Mining Hose Supports Demanding Operations

Mining environments place considerable demands on equipment used for material transfer, water management and processing. Hoses operating in these co...

Simple Ideas for Making Social Gatherings More Memorable

We have all been to those parties where everyone just stands around the kitchen island, staring at their phones, waiting for someone else to make a mo...

Outdoor Wall Lights: Improving Exterior Lighting Around Your Home

Lighting can influence how a room looks, feels and functions, so the right fitting should be selected according to both appearance and practical req...

Commercial Office Cleaning: Combining Routine Office Cleaning With Melbourne Service

Keeping a workplace clean requires a service that can accommodate everyday tasks as well as the particular needs of the business. Professional comme...

Caravan Sales in Queensland: How to Find the Right Caravan for Sale QLD

Caravan ownership is about more than having somewhere to sleep while travelling. For many Queenslanders, it is one of the best ways to explore regio...

What Sir Walter Buffalo Turf Actually Costs in 2026 (And Why Quotes Vary So Much)

Two quotes landed on a Hills District homeowner's kitchen table last spring for the exact same 80-square-metre backyard. One said $12 a metre. The o...